An Update on the status of the Elevator modernization.
Royal Park condos Apartments, Inc.
An Update on the status of the Elevator modernization.
· The electrical Updated to code is 90% Completed.
· The New Packing for all cylinders are Completed.
· The New Machine Room door are installed and the self-closing hardware is being adjusted for correct operation.
· The skins for the outside doors have started and are being installed now.
· We feel the modernization is going well and will be completed in a timely manner
. We are almost complete with all machine room upgrades we have two pumping units left.
. The Fire Company (Armer) are working hard, and have half the complex complete.
. The New Stainless on two elevators complete.
. They are working diligently to get them all done. the controllers are set to ship next week. They will start to install them as soon as they arrive and let all residences know anytime the elevator will be down.
. Rev 02/19/20233 = lane Elevator will finish 112 and 113 and go onto building 103 and 117. We need ti get ti the problem elvators first.
Best Regards,
Lane Elevator, Inc